It was actually several weeks ago, but we learned that for every door that a contractor may need to get through, all keys should be provided rather than just enough for one lock in each door. For reasons known only to him, our foreman decided one morning to lock both the deadbolt and the knob on the back door, which had different locks. Note the past tense – we weren't home the next morning when the crew arrived. So Chris told them to break the doorknob off in order to open the door. We think they used a shovel, given the amount of dirt left behind. Really, this is a lesson for everyone to ensure they install high quality door hardware!
The contractors had ripped down the ceilings and the old roof and now were in build mode… mostly. The first step was to install floor joists across the span of the house so the framers have something to stand on while building up from there.
As they built up, they needed ready access to the space above, which meant they built stairs! For the record, these are temporary stairs as we are still working with Allison (our designer) on the final design.
While building up, they installed a load-bearing beam down the centreline of the house, along with posts to hold up the load of the new upper floor. The original plan was to rebuild the same wall that existed between the living room and master bedroom so as to avoid extra permitting fees from the city. Permit fees are directly proportional to project cost and the amount of renovated floor space.
But then something funny happened at some point between Friday morning, when we left for work, and Friday evening when we came home. Originally there were walls around the kitchen, with ancient cabinets installed on them. The plan was to work around and preserve (or remove if necessary) the cabinets, which we think were original to the house. Unfortunately they had been built in place and could not be taken out whole, which meant that on that Friday a few weeks ago, they were reduced to kindling by the crew. It appears we are in the market for a new kitchen and need to rethink the main floor plan accordingly. This is still a work in progress as we definitely do not want to trigger the additional permit fees the city could charge us!
After the destruction of the kitchen and some other top floor work on Saturday, the construction crew decided to take Sunday off. Which meant it was time for Chris and me to do some much-needed tidying and to provide some assistance with the construction process. This was only somewhat challenging as there is no heat, no wall insulation, hardly any roof overhead plus there are holes the size of fists in the exterior wall AND it was a bloody cold day! I was wearing 4 layers of shirts, 2 sets of socks, a knit hat and cheap construction gloves to minimize the shivers.
My job that day was to pull out all the drywall nails that remained in the walls of the space that was once the kitchen. Chris, I believe, did more technical and advanced construction type stuff that involved lots of hammering and using various power tools. Next time I'll take an action shot of him.
As the house went up, the tarp was also being raised just a bit higher – just in time for another set of major wind storms in Vancouver. We present the "Good Ship Waterhouse" as it existed in the 3rd week of November.
Eventually came a day that we could actually go upstairs and walk around on the new "top floor".
By the last week of November, the contractors had installed the upper-floor framing for the west wall and were working on the other three walls. It is strange to see the plywood sheathing going right over the window openings, but I guess that's how it's done. I still don't have a good feeling for how big our windows are as the framing is several inches bigger than the glass to accommodate the window frames.
We also learned why we have so many different people reviewing the framing in this phase. Chris and I walked around the top floor, took photos and commented on the future view. Allison came by and noticed that the side walls had been framed out too far to the south to accommodate the "pop-out" wall on the front for a window seat in the bedroom and tub in the master bathroom. Very simple to fix now, not so much later.
I was first confused when I saw this left-behind section until Chris explained what in the world was going on. The crew left a section of the old wall, and it will actually remain up for some time as they work around it with the new construction.
The other side of this piece of wall is the point where the main power lines are anchored to the house. Eventually the attachment point for electricity and telephone wires will shift to a new home. This too is a decision in the making.














































